From the desk

Articles

Project delivery written by someone still doing it. The reasoning first, then the tool, template or diagram that makes it usable on Monday.

SPI and CPI: the two ratios that say if you are late or over budget

Two ratios off one earned value figure. SPI divides it by the plan and reads schedule. CPI divides it by the bill and reads cost. Below 1 is bad news in both, for different reasons.

6 August 2026
Earned value management: what EV, PV and AC actually measure

Three figures read at one date. Planned value is what the baseline said would be finished by now, earned value is what did finish, actual cost is what finishing it cost.

5 August 2026
Tornado diagrams: reading a sensitivity analysis at a glance

One bar per variable, the widest at the top, all of them measured against a baseline down the middle. A tornado diagram ranks what could move an outcome, and by how much.

4 August 2026
Risk register versus issue log: what goes in each, and the moment one becomes the other

A risk might happen. An issue already has. That single difference decides which artefact a line belongs in, what you record about it, and who you have to tell.

3 August 2026
The stakeholder engagement assessment matrix: current, desired, and the gap between

One row per stakeholder, one column per engagement level, and two marks per row. The distance between the two marks is the only thing on the grid you can actually act on.

2 August 2026
The salience model: sorting stakeholders by power, legitimacy and urgency

Three attributes, seven classes, one question: whose claim gets attention first. Hold all three and you are a definitive stakeholder, and definitive stakeholders do not wait.

1 August 2026
Closing an agile project: ending work that could always run one more sprint

Predictive work gets an ending for free, the day the thing is handed over. Iterative work has to manufacture one, which is why so much of it never formally ends at all.

31 July 2026
Delivery cadence: the rhythm you work to, and how often something actually ships

Cadence is the beat the work runs to. Delivery cadence is how often finished output reaches the people who asked for it. Teams conflate the two and then wonder why nobody feels the pace.

30 July 2026
Legal concepts in project management: what to recognise, record and escalate

A delivery manager does not need to know contract law. They need to notice the moment a delivery problem becomes a contractual one, because after that moment informal handling starts costing money.

29 July 2026
Contingency reserve vs management reserve: what sits inside the baseline, and who releases it

Contingency reserve sits inside the cost baseline, for risks already named and priced. Management reserve sits above it, for the ones nobody named. Level and authority, not size.

28 July 2026
Rewards and recognition: the lever with a budget, and the one you actually hold

A reward is set in advance and conditional. Recognition is retrospective, unexpected and free. Most project managers control the second and none of the first, which decides where the effort goes.

27 July 2026
Types of PMO: which one you have, and which one the work is asking for

Three types, separated by one variable: how much authority the office holds. Supportive advises, controlling requires, directive runs the work. Level is a second axis and a different question.

26 July 2026
Iteration-based and flow-based agile: one fixes the interval, the other fixes the queue

Iteration-based agile fixes the length of the cycle and commits a batch to it. Flow-based agile fixes the amount of work in progress and pulls the next item when a slot frees.

25 July 2026
Needs assessment: establishing the gap before anyone names a solution

A needs assessment measures the distance between the current state and the state an organisation requires, in evidence rather than assertion, and it does it before any solution is named.

24 July 2026
Make or buy decisions: compare whole life costs, then decide on what cost cannot show

A make or buy analysis compares the whole life cost of building something against buying it, and finds the point where the cheaper option changes. Capability, control and risk usually decide it.

23 July 2026
Inherent, residual, and the score nobody writes down

Most risk registers record one number per row. The number that actually justifies spending money is the distance between two of them.

22 July 2026